Ham Nghi - Vung Ang highway shape

VnExpress - VN Express - 12:08
Ha Tinh - Ham Nghi - Vung Ang highway is invested more than VND 9,700 billion, when operating, it will shorten the journey of Hanoi - Ky Anh town from 8 to 6 hours.

The Ham Nghi - Vung Ang highway is nearly 54 km long in January 2023, a budget of more than VND 9,700 billion. The first point of the project in Thach Xuan commune, Thach Ha district, connecting Bai Vot - Ham Nghi highway. The end point at the intersection of Ky Tan commune, Ky Anh district, connected to Vung Ang - Bung expressway.

Pictured is the intersection with Bai Vu - Ham Nghi highway, belonging to Thach Xuan commune, Thach Ha district, also the first point of the project.

The Ham Nghi - Vung Ang highway is nearly 54 km long in January 2023, a budget of more than VND 9,700 billion. The first point of the project in Thach Xuan commune, Thach Ha district, connecting Bai Vot - Ham Nghi highway. The end point at the intersection of Ky Tan commune, Ky Anh district, connected to Vung Ang - Bung expressway.

Pictured is the intersection with Bai Vu - Ham Nghi highway, belonging to Thach Xuan commune, Thach Ha district, also the first point of the project.

On April 19, Ham Nghi - Vung Ang highway was organized by the Ministry of Construction. Up to now, the project has completed more than 97% of the work volume, expected to start exploiting the main route from April 28.

In order to implement the project, authorities must recover more than 488 hectares of agricultural land, residential land, forest land and other types of land. The total number of households who have to resettle is 195. Cam Xuyen district has the highest number of households, with 88, arranged 8 resettlement areas.

On April 19, Ham Nghi - Vung Ang highway was organized by the Ministry of Construction. Up to now, the project has completed more than 97% of the work volume, expected to start exploiting the main route from April 28.

In order to implement the project, authorities must recover more than 488 hectares of agricultural land, residential land, forest land and other types of land. The total number of households who have to resettle is 195. Cam Xuyen district has the highest number of households, with 88, arranged 8 resettlement areas.

In the first phase, the highway has 4 lanes, 17 m wide roads, maximum speed of 90 km/h, minimum 60 km/h. In the complete stage, the road will have 6 lanes, the maximum design speed of 120 km/h.

In the first phase, the highway has 4 lanes, 17 m wide roads, maximum speed of 90 km/h, minimum 60 km/h. In the complete stage, the road will have 6 lanes, the maximum design speed of 120 km/h.

Some of the highways passing the hill, the construction unit must fined and designed the anti -landslide system.

Some of the highways passing the hill, the construction unit must fined and designed the anti -landslide system.

The contra...